Hello,

we are using SSRS report to build Project plan report and display within another application.

-We are able to group activities for each quarter and display the boundaries for each quarter but we are not able to change the Text legend as Quarter ( instead it appears as Jan, Feb, etc not as quarter 1-2015)

- We wanted to define few activities as Phases..and dates as managed in X-column and we are not able to read the X-column parameter of start and Date date for any phase to define boundary for each phases.

-Is their way to place the Text of Milestone legend in the Report above the milestone legend image which is shown as display. since the text of milestone legend is overlapping on the activity text.

-Is their a way to align text (dates on X-column) which are close to each other -Above and below (every alternate text) for readable purpose else it looks cluttered.

Regards,
Steve
Posted

This content, along with any associated source code and files, is licensed under The Code Project Open License (CPOL)



CodeProject, 20 Bay Street, 11th Floor Toronto, Ontario, Canada M5J 2N8 +1 (416) 849-8900